Piled raft foundation.
Foundations

Piled Raft Foundation

We completed the entire project from excavation to pouring 12m³ of concrete...

Date:
July 1, 2024
Location:
Lewes
Client:
Bush and Grimes Construction ltd
Project Value:
Project Details

About the Project

We were awarded the whole project from breaking ground to pouring concrete. Our groundworks team started with excavating 600mm down from existing ground level to formation level. We then cut and broke piles to the correct level. We installed 225mm anti heave cell-core to the entirety of the raft. We then installed DPM and all steel reinforcement including Beamform around the perimeter to retain the pour.

Finally we placed and finished 12m3 of c35 concrete from a line pump. Was great to work with Platinum Groundworks on this one!

No items found.